How To Report On Activities With Notebook Topics In P6 Project Management (Doc ID 901850.1)

Last updated on AUGUST 12, 2016

Applies to:

Primavera P6 Professional Project Management - Version 5.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 5.0 and later
Primavera Contractor - Version 5.0 to 6.1 [Release 5.0 to 6.1]
All Platforms
***Checked for relevance on 02-Dec-2011***
***Checked for relevance on 20-May-2013***

Goal

This document explains how to create a report on Activities with Notebook Topics in P6 Project Management.