Performance % Complete Is Not Equal To Activity % Complete (Doc ID 902148.1)

Last updated on JUNE 29, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 5.0 and later
All Platforms
***Checked for relevance on 27-Jul-2012***


Symptoms

Performance Percent Complete is not equal to Activity Percent Complete even though Activity Percent Complete is selected as the technique for computing Performance Percent complete.

Cause