PrmConvert.ini Settings To Modify The Resource Type Of A P3 Default Unit Of Measure When Importing Into Project Management Is Not Working (Doc ID 902176.1)

Last updated on JUNE 30, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version: 5.0 and later   [Release: 5.0 and later ]
Primavera Contractor - Version: 5.0 to 6.1   [Release: 5.0 to ]
All Platforms
***Checked for relevance on 18-Aug-2010***

Symptoms

The PrmConvert.ini settings are not working when importing P3 projects into Project Management and wishing to modify the resource type of a P3 default unit of measure.

Cause