Modifying The 'Action' For Activity Date Types In One XER Import Template Changes Activity Resource Assignment Data For All Other Templates (Doc ID 902343.1)

Last updated on JUNE 30, 2016

Applies to:

Primavera P6 Professional Project Management - Version 3.5 to 6.2.1 SP2 [Release 3.5 to 6.2]
Primavera P6 Enterprise Project Portfolio Management - Version 3.5 to 6.2.1 SP2 [Release 3.5 to 6.2]
All Platforms
***Checked for relevance on 09-Jun-2011***


Symptoms

When modifying import configuration layouts (for XER import), changing the 'Action' for the Activity data types in one template, will change the Activity Resource Assignment Data Type's Action for all other Import Configuration layouts.

For example, if you change the Action from "Update Existing" to "Keep Existing" in one Import Configuration, this change will also be applied to the Activity Resource Assignments data type in other Import Configurations.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms