Actual Units Are Updated When An Actual Finish Is Applied To The Resource Assignment (Doc ID 903814.1)

Last updated on JULY 31, 2017

Applies to:

Primavera P6 Professional Project Management - Version 6.1 and later
Primavera P6 Enterprise Project Portfolio Management - Version 6.1 and later
All Platforms

Symptoms

Actual units are updated when an Actual finish is applied to the resource assignment.  On a resource assignment with zero Actual Units, when an Actual finish is applied to the resource assignment, the Actual Units are set to the Remaining Units and the Remaining Units are then set to zero.

 

For example,

The activity is in progress, but no work has been done by the resource and Actual Units are zero.

Cause