Durations Are Incorrect After Importing A Microsoft Project (MSP) File (Doc ID 905210.1)

Last updated on JULY 05, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 5.0 and later
Primavera Contractor - Version 5.0 and later
Primavera P6 Professional Project Management - Version 5.0 and later
All Platforms
***Checked for relevance on 16-Oct-2012***

Symptoms

Durations and dates are different or wrong after importing a Microsoft Project (MSP) file into Primavera P6.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms