How To Edit Budgeted Total Cost And Actual Total Cost For An Activity? (Doc ID 905516.1)

Last updated on JUNE 23, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 5.0 to 8.0 [Release 5.0 to 8.0]
Primavera Contractor - Version 6.1 and later
All Platforms

Goal

These fields cannot be edited in the Activity Level because they're calculated fields.

Budgeted Total Cost = Budgeted Labor Cost + Budgeted Non-labor Cost + Budgeted Material Cost + Budgeted Expense Cost

Actual Total Cost = Actual Labor Cost + Actual Non-labor Cost + Actual Material Cost + Actual Expense Cost

Solution