Planned Value Cost is Not Obeying Custom Resource Curve when Separate Baseline is Assigned.

(Doc ID 906772.1)

Last updated on JULY 05, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version: 6.0 - Release: 6.0
Primavera P6 Professional Project Management - Version: 6.0 - Release: 6.0
Primavera Contractor - Version: 6.1
All Platforms
***Checked for relevance on 30-Mar-2010***

Symptoms

When showing the Planned Value Cost curve in the Activity usage profile it shows based on the Resource curve when the Current Project is assigned as a baseline. 

However, when a copy of the project is saved as the baseline, the curve changes to a linear spread.

See the following screen captures for an example to this issue:

Before assigning separate baseline:

 >" id="list0" class="uneditablelink" />

After assigning a separate baseline:

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms