Is there the ability to set different date points to certain dates on an Activity's bar in the Gantt chart? (Doc ID 906930.1)

Last updated on JULY 05, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version: 6.1 and later   [Release: 6.1 and later ]
Primavera Contractor - Version: 6.1 and later    [Release: 6.1 and later]
All Platforms

Goal

The ability to set different date points to certain dates on an Activity's bar in the Gantt chart.

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms