Output To CSV From A Claim Digger Report Extending Pushing The Activity Description Into Multiple Cells

(Doc ID 907755.1)

Last updated on JULY 05, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 6.1 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 8.2.4.0 and later
Primavera P6 Professional Project Management - Version 6.1 and later
All Platforms

Symptoms

When attempting to save a Claim Digger / Schedule Comparison report to CSV, the 'Activity Description' value is extended into multiple excel cells.

Cause