Will Update Baseline Work If Any Activity Assignments Are Using Manual Curves With Future Bucket Planning? (Doc ID 907774.1)

Last updated on JULY 05, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version: 6.2.1 and later   [Release: 6.2 and later ]
All Platforms

Goal

Will Update Baseline work if any Activity Assignments are using manual Curves with Future Bucket Planning?



Your project/baseline contains future bucket data. You cannot run Update Baseline against it.

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms