Goal

This document explains how to replace Resource Assignments with a different Resource when the Activity is In-Progress (Started) and/or has Actuals.
  • "Cannot change Resource because the previous Resource already has Actuals."
  • "Cannot change Resource because the previous Resource already has Financial Period Data stored."
When a Resource Assignment has Actuals, P6 will not allow the user to replace the Resource for that Assignment with a different Resource.

Instead, the user must delete the Resource Assignment and add a new Assignment, then manually assign the Actuals to the new Resource Assignment.

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms