When Running 'Import From Contract Manager', Activities Linked To Line Items Within Contract Manager Are Not Being Updated With Expense And Cost Account Information (Doc ID 908254.1)

Last updated on JULY 31, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version: 5.0 and later   [Release: 5.0 and later ]
Primavera Contract Management - Version: 12.1 and later    [Release: 12.0 and later]
All Platforms
***Checked for relevance on 22-Apr-2011***

Symptoms

When running 'Import from Contract Manager', Activities linked to Line Items within Contract Manager are not being updated with Expense and Cost Account information.

Cause