Project Management XML Import Times Out Or Takes An Extrememly Long Time When Connecting To An Oracle Database Hosted On An AIX Server (Doc ID 911530.1)

Last updated on JUNE 29, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version: 6.1 to 6.1 - Release: to 6.1
Primavera P6 Professional Project Management - Version: 6.1 to 6.1 - Release: 6.1 to 6.1
All Platforms

Symptoms

When performing an XML Import in Project Management, the XML import times out or takes an extremely long time when the database is using an Oracle backend hosted on an AIX Server.

The following exception is also received in the log file:
SEVERE: Connection has been recycled. Database P6PR Pool PMT
com.primavera.PhoenixException: Connection has been recycled. Database P6PR Pool PMT



Cause

Sign In with your My Oracle Support account