Modifying Remaining Units at the Activity Level Removes Actual Finish From Resource Assignments (Doc ID 911748.1)

Last updated on JUNE 28, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 6.1 and later
All Platforms

Symptoms

Modifying Remaining Units at the Activity level removes Actual Finish from Resource Assignments.

 EXAMPLE:

Changing Remaining Units at the Activity level removes Actual Finish dates from Resource Assignments under the following scenario:

1. Start with an Activity that has an AS(Actual Start) and some of the assignments have AF(Actual Finish) dates.

Cause