Modifying Remaining Units at the Activity Level Removes Actual Finish From Resource Assignments (Doc ID 911748.1)

Last updated on JULY 11, 2018

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 6.1 and later
All Platforms

Symptoms

Modifying Remaining Units at the Activity level removes Actual Finish from Resource Assignments.

 EXAMPLE:

Changing Remaining Units at the Activity level removes Actual Finish dates from Resource Assignments under the following scenario:

1. Start with an Activity that has an AS(Actual Start) and some of the assignments have AF(Actual Finish) dates.

2. Zero out the Remaining Units at the assignment level.

3. Enter a new value for Remaining Labor Units at the Activity Level. Notice that the AF is removed from all assignments.

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution

My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.