Export From P6 to P3 Only Brings In The Resources For The First Three Activities (Doc ID 911923.1)

Last updated on JULY 05, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version: 5.0 and later   [Release: 5.0 and later ]
Primavera Contractor - Version: 5.0 to 6.1   [Release: 5.0 to ]
All Platforms
***Checked for relevance on 14-Feb-2011***

Symptoms

Projects exported from Project Manegement to P3 only bring in the Resources for the first three Activities, so resource assignments are missing in P3.

Cause

Sign In with your My Oracle Support account