Timesheets Help Is Wrong With Regard to Updating Activities With Suspend/Resume Dates. (Doc ID 912001.1)

Last updated on JUNE 28, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 6.1 to 7.0 [Release 6.1 to 7.0]
All Platforms

Symptoms

Timesheets Help is wrong with regard to updating Activities with Suspend/Resume Dates. Incorrect help information in Timesheet online help about Suspend date. Primary Resource is able to mark an Activity as Finished and edit the Expected Finish Date in Timesheets when Activity is Suspended.

Cause