Updating Remaining Duration Changes Actual Units And Actual Costs (Doc ID 912008.1)

Last updated on AUGUST 25, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 5.0 and later
Primavera P6 Professional Project Management - Version 5.0 and later
Primavera Contractor - Version 5.0 and later
All Platforms
***Checked for relevance on 09-Oct-2012***

Symptoms

For an Activity set as Duration Type 'Fixed duration and units' or 'Fixed duration and units/time,' updating Remaining Duration changes Actual Units and Actual Costs.

Scheduling causes the Remaining Units and Remaining Costs to change on resource assignment.

Cause