Updating Remaining Duration Changes Actual Units And Actual Costs

(Doc ID 912008.1)

Last updated on AUGUST 25, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 5.0 and later
Primavera P6 Professional Project Management - Version 5.0 and later
Primavera Contractor - Version 5.0 and later
All Platforms
***Checked for relevance on 09-Oct-2012***

Symptoms

For an Activity set as Duration Type 'Fixed duration and units' or 'Fixed duration and units/time,' updating Remaining Duration changes Actual Units and Actual Costs.

Scheduling causes the Remaining Units and Remaining Costs to change on resource assignment.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms