Remaining Units Recalculate To Zero (0) On WBS Summary Activities (Doc ID 912118.1)

Last updated on JANUARY 21, 2014

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 3.5 and later
Primavera Contractor - Version 4.0 and later
Primavera P6 Professional Project Management - Version 3.5 and later
All Platforms
***Checked for relevance on 21-Jan-2014***

Symptoms

Remaining Units and Remaining Duration is calculated incorrectly on WBS Summary activity because Remaining Units recalculate to zero (0) on WBS Summary Activity Resource Assignments.

Steps to reproduce:

1) Create a new project with one WBS (only need the root node)
2) Add four activities to this WBS
3) Change two activities to Start Milestones
4) Change one to a Finish Milestone
5) Change one to a WBS Summary
6) Assign a resource to the WBS summary and give it 100 Budgeted and Remaining Units
7) Schedule, and the units recalculate to 0

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms