Update Baseline Option to Add New Resource and Role Assignments Does Not Update Baseline Resource Assignments (Doc ID 912252.1)

Last updated on JUNE 29, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 6.0 to 7.0 [Release 6.0 to 7.0]
Primavera P6 Professional Project Management - Version 6.0 to 7.0 [Release 6.0 to 7.0]
All Platforms
***Checked for relevance on 19-Apr-2013***

Symptoms

Add new resource and role assignments option does not update baseline resource assignment.

Update baseline function Add new resource and role assignments. 

The activity had 3 resources assignment. 

Cause