How To Group So That Each Resource Is Listed Individually

(Doc ID 912733.1)

Last updated on JULY 05, 2016

Applies to:

Primavera P6 Professional Project Management - Version 5.0 and later
Primavera Contractor - Version 5.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 5.0 and later
All Platforms

Goal

In the Activities View, each activity can only be listed once. Therefore, when grouping by resource, activities are grouped according to their resource assignments as a combination.  Each different combination of resource assignments is a group band with the activities holding that combination listed below.