Guide to Cost and Resource Uncertainty in Primavera Risk Analysis. (Doc ID 912826.1)

Last updated on SEPTEMBER 19, 2019

Applies to:

Primavera Risk Analysis - Version 8.0 and later
All Platforms

Purpose

This document explains the most basic ways to assign cost and resource uncertainty in Primavera Risk Analysis.  There are additional ways to assign risk and uncertainty and work with costs and resources, but this document will cover:

The "Other Methods" section at the bottom mentions some additional options for working with resources, costs, and their risk/uncertainty.

Scope

This document is appropriate for users who understand how to create and assign resources in Primavera Risk Analysis, but need more information on the basics of resource and cost uncertainty.

Details

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Purpose
Scope
Details
 Overview
 Resource Uncertainty at the Task Level
 Cost Uncertainty at the Resource Level
 Duration Dependent Resource Assignments
 Other Methods for Assigning Resource and Cost Risk/Uncertainty