In The Summary Risk Report, When Reporting On Correlation Between Task Existence, The Percentage Column Should Show 100%

(Doc ID 913207.1)

Last updated on JULY 12, 2016

Applies to:

Primavera Risk Analysis - Version: 8.5.0049 to 8.5.0049 - Release: 8.5 to 8.5
All Platforms

Symptoms

In the Summary Risk Report, when reporting on correlation between task existence, the percentage column should show 100% (meaning there is 100% correlation between the task existences), not the probability of the task existences.

Task Existence Percentage being shown instead of Correlation Percentage.

Cause