Probabilistic Cash Flow - Percentile Per Period Values Do Not Match Percentile Cumulative Values. (Doc ID 913740.1)

Last updated on AUGUST 18, 2019

Applies to:

Primavera Risk Analysis - Version 7.8 and later
All Platforms
Checked for relevance on October 19th, 2011.

Symptoms

Understand risk results in the probabilistic cash flow.

Why do Percentile per period values not add up to the same as the Percentile cumulative values? 

P20, P50, P80 & any percentile value created by user. The sum of percentile per period values does not equal the percentile cumulative values.

 

In example above looking as far as period 2 the per period values of $28,382 + $39,964 = $68,346.

The cumulative value for period 2 is $65,407.

The sum of per period values is $132,532 but the cumulative total is $127,776

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution