How To Change The Order Of WBS Bands When Grouped By WBS (Doc ID 914573.1)

Last updated on JULY 12, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version: 5.0 and later   [Release: 5.0 and later ]
Primavera Contractor - Version: 5.0 and later    [Release: 5.0 and later]
All Platforms
***Checked for relevance on 12-Apr-2011***

Goal

This document explains how to change the order of WBS bands when grouped by WBS.

Having a) Entered a new 'WBS' level in the 'Work Breakdown Structure' view:

The WBS bands are ordered in the Activity View as they appear in the hierarchical view in the WBS View. The cause of the discrepancy is that the WBS view was not in 'hierarchical' mode when the new value was added.

Solution