DRP - Create And Reschedule ISO Failed When Across Multiple OU's (Doc ID 943244.1)

Last updated on FEBRUARY 18, 2019

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.0.4 and later
Information in this document applies to any platform.
MSCRLISO module: MSC Create and Reschedule ISO



Symptoms

On 12.0.4/12.0.6
When attempting to create Internal sales order, request MSC CREATE AND RESCHEDULE ISO is failing with following error

ERROR
Error :1 Validation failed for the field - Order Type

STEPS
The issue can be reproduced at will with the following steps:
1. Responsibility : Distribution Planning
2. Navigation : DRP Planner Workbench, release a planned order or reschedule recommendation for Internal Req/ISO pair from DRP Plan.
3. It fails with error when the releases happen for lines for orgs that reside in different Operating Units (OU)

Example:
Plan is defined in ORGA which is part of OU1
Plan also includes ORGB which is part of OU2
When releasing planned shipment orders for ORGB, errors will occur.

BUSINESS IMPACT
The issue has the following business impact:
ISO cannot be created

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!