MEMORY BASED PLANNER FAILS FOR DEMAND HAVING QUANTITY > 100 (Doc ID 975658.1)

Last updated on MARCH 30, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 11.5.10 and later
Information in this document applies to any platform.

Symptoms

When attempting to run ASCP plan with demand having quantity > 100, the following error occurs. (If demand quantity and number of data is less, MBP completed without any error.)

mrpcal_date_offset: There is a Problem .....after call to mrpcal_cached_cal OG:OG US 01

APP-MRP-22064: An internal error has occurred (mrlups_update_supply, 501)
Cause: The current routine encountered the specified internal error.
Action: Contact your customer support representative.


The issue can be reproduced at will with the following steps:

1. Advanced Supply Chain Planner Responsibility
2. Run ASCP with demand having quantity > 100.

Cause

Sign In with your My Oracle Support account