Message 'The scheduler process requires additional time to complete. You can continue to work while the process completes in the background.' When Running a Schedule Operation in P6 (Doc ID 1535642.1)

Last updated on MARCH 22, 2022

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 8.1.1.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 8.4.0.0 and later
Information in this document applies to any platform.

Symptoms

When running an on-demand schedule operation in P6, regardless of the project size the following message is displayed and requires the Activities view to be refreshed in order to see the schedule changes:

The scheduler process requires additional time to complete. You can continue to work while the process completes in the background.

This issue can be perceived as a performance issue.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution