Message: "The scheduler process requires additional time to complete. You can continue to work while the process completes in the background" Running A Schedule Operation In P6 (Doc ID 1535642.1)

Last updated on MARCH 31, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 8.1.1.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 15.2.0.0 and later
Information in this document applies to any platform.

Symptoms

When running an on-demand schedule operation in P6, no matter the size of the project, the following message is displayed and requires the activities view to be refreshed in order to see the schedule changes which can be perceived as a performance issue:

MESSAGE
------------------
The scheduler process requires additional time to complete. You can continue to work while the process completes in the background.

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms