Incrementing Argument Value For Benefits Processes (Doc ID 1637640.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Fusion Benefits Cloud Service - Version 11.1.5.0.0 and later
Information in this document applies to any platform.

Symptoms

When attempting to schedule a recurring Evaluate Life Event Participation, Close Enrollment and Purge Backed-Out or Voided Life Event Data process, and set an initial effective date, the process runs everyday but it runs as of the effective date that was originally set.

STEPS
-----------------------

1.Go to Navigator > Select Evaluation and Reporting.
2.Choose Benefits Administrator Work Area Task in Left Hand Menu.
3.In the Summary Area, select the Process Tab.
4.Select Evaluation Summary Process Life Events group.
5.Click on Submit button against Evaluate Life Event Participation, Close Enrollment and Purge Backed-Out or Voided Life Event Data process
6.Effective Date of the process is defaulted to sysdate
7.Click the Advance Button.
8.Select Schedule Tab.
9.select Run as Using a Schedule.
10.Select Frequency : Daily  / Every:  1 Day / Start date :10-01-2013 12:06 PM / End Date :  12-31-2014 12:06 AM
11.Click on submit button

Run 1: October 1st, Effective date: October 1st
Run 2: October 2nd, Effective date: October 1st expected effective date is October 2nd
Run 2: October 3rd, Effective date: October 1st expected effective date is October 3rd

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms