Grouping Band Indent Level In Activity View Is Incorrect For New WBS Nodes And A Duplicate WBS Band Is Displayed (Doc ID 1682068.1)

Last updated on FEBRUARY 29, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 7.0 and later
Primavera P6 Professional Project Management - Version 7.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 8.2.4.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
When creating new WBS elements in the WBS view, and then navigating to the Activity view (which is grouped by WBS), the indent level of the new WBS elements is wrong, and there is a duplicate WBS shown.

In the Activity view, the first newly added WBS (WBS1) is shown at the child level to WBS above it (should be sibling), a duplicate WBS1 is at the correct level, and the second newly added WBS (WBS2) is shown as a child of the correct level WBS1.

EXPECTED BEHAVIOR
-----------------------
The new WBS nodes should be displayed at the correct grouping indent level in the Activity view.

STEPS TO REPRODUCE
-----------------------
1. Open a Project
2. Navigate to the WBS view
3. Under WBS Name ABC1 add two new WBS nodes at the same level, ABC2 and ABC3
4. Navigate to Activity view, and see ABC2 shown at the child level to ABC1, see a duplicate ABC2 at the correct level, and see ABC3 as a child of ABC2

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms