Fusion Global HR: Date Entered For Dec 31-4712 In Calendar Is Taking As Dec 31-2012 (Doc ID 1961287.1)

Last updated on SEPTEMBER 06, 2016

Applies to:

Oracle Fusion Global Human Resources Cloud Service - Version 11.1.8.0.0 and later
Oracle Fusion Global Human Resources - Version 11.1.8.0.0 and later
Information in this document applies to any platform.

Goal

Working on HCM Extracts. While running Report from Payroll Checklist,
1) Select Flow pattern. Next
2) In the Enter parameters page After giving the payroll flow name, in the process End Date, when I select the date from calendar for "Dec 31- 4712' after its selected , it is showing as 12/31/12
but when the report is run, it is actually taking the value as "2012-12-31" .
Likewise, year entered for 2099 is taking it as 1999.
 

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms