Goal

On : 11.1.9.2.0 version, Other Issues

User has currently 1000+ task and sub-tasks in EBS R12.1.3. User need to integrate these project/tasks into Oracle Fusion Projects Execution Management (PJT). How can we maintain/retain the same project number and the task number in Oracle Fusion Projects Execution Management (PJT).

Navigator>Project Manager Dashboard> Create a Project> Create Tasks
 

Solution