Symptoms

ACTUAL BEHAVIOR
---------------
Modifications for the Project Schedule Sheet were not logged in Audit Log.

EXPECTED BEHAVIOR
-----------------------
Any modification should be recorded by Audit Log for the Project Schedule Sheet.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

  1. Log in as a Company Administrator.
  2. Go to any Project.
  3. Locate and expand node - Schedule Manager.
  4. Locate and Click sub node - Schedule Sheets.
  5. Click to open on item - Project Schedule Sheet.
  6. Click on the down arrow button next to button and select Add.
  7. Choose Manual to add Activity.
  8. Add any Activity
  9. Save the changes.
  10. Locate menu item - Audit Log on the Schedule Sheet page and select it.
  11.  Audit Log shows:
    08/03/2015 02:07 AM Schedule Sheet Open sheet: Project Schedule Sheet Company Administrator: Oracle Site Administrator
    08/03/2015 02:29 AM Schedule Sheet Open sheet: Project Schedule Sheet Company Administrator: Oracle Site Administrator
    08/03/2015 02:29 AM Schedule Sheet Open sheet: Project Schedule Sheet Company Administrator: Oracle Site Administrator
    08/03/2015 02:33 AM Schedule Sheet Open sheet: Project Schedule Sheet Company Administrator: Oracle Site Administrator

    No modification records for the Schedule Sheet are logged.


BUSINESS IMPACT
-----------------------
Due to this issue, users cannot verify what modifications made to Project Schedule Sheet.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms