Project Budgets Edit In Excel Not Updating Total Budget Cost And Giving Error (Doc ID 2043867.1)

Last updated on FEBRUARY 03, 2019

Applies to:

Oracle Fusion Project Control Cloud Service - Version 11.1.8.0.0 and later
Information in this document applies to any platform.

Symptoms

When trying to edit a project budget in excel the following error is received in the application:

The message is synchupReportingDataJBO-25014: Another user has changed the row with primary key oracle.jbo.Key[10000001231682]..

After clicking through the Project and any roll-up task totals are not updated correct.The Budget Version total does not update correctly.

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


This document is being delivered to you via Oracle Support's Rapid Visibility (RaV) process and therefore has not been subject to an independent technical review.
My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.