Unable to Change the Owner of an Issue in Instantis EnterpriseTrack (Doc ID 2085667.1)

Last updated on DECEMBER 21, 2015

Applies to:

Instantis EnterpriseTrack - Version 9.0.2.0 and later
Instantis EnterpriseTrack Cloud Service - Version 9.0.2.0 and later
Information in this document applies to any platform.

Symptoms

When attempting to change an Issue owner to a resource assigned to the project, the following error occurs.

ERROR
-----------------------
Error while showing Basics Page. Please correct the errors shown below, and try again.
For the role <ROLE NAME>, Plan Percent Availability cannot be provided if the checkbox for Assigned is not checked.
For the role <ROLE NAME>, Actual Percent Availability cannot be provided if the checkbox for Assigned is not checked.

Cause