Symptoms

On : 11.1.9.2.0 version, Manage Project Costs-Process Project Cost Transactions

Nightly processes were just recently setup to run and it was discovered that all Payables transactions being interfaced to Projects are failing. There is a Ledger Control Budget in place which is causing the error -

Error
Invalid account on transaction.

Replication Steps
1. Budgetary Control was setup at the Ledger level.
2. Supplier Invoice with PTEO created.
3. Run the Import and Process Transactions and select Fusion Payables.
4. Actions>View Budgetary Control Amounts shows the error.

Cause

Sign In with your My Oracle Support account