Symptoms

In the Project Codes dictionary, if one Project Code Weight is modified, all the other Project Codes Weight values are not re-calculated, even after the last changes are saved. The correct values appear only after reloading the page (F5).

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

1. Open "Project Codes" dictionary dialog from Administer, Enterprise Data.
2. Using sample data, select Code Weight, (i.e. for the existing 'Strategic Rating' Code, modify Weight from 30.0 to 25.0 (note Weights for other Codes).   Click Save. Weight Percent for 'Strategic Rating' adjusted to reflect Weight change.
3. Note Weights for all other Codes have not changed. Refresh page or change to another view and come back to Projects Codes dictionary.  Note Weight Percent for other Codes have changed.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms