Activities Pasted From Another Project Only Show All Assignments When Both Projects Are Open (Doc ID 2096823.1)

Last updated on JANUARY 21, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 15.2.1.0 to 15.2.2.0 [Release 15.2]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 15.2.1.0 to 15.2.2.0 [Release 15.2]
Primavera P6 Professional Project Management - Version 15.2.1.0 to 15.2.2.0 [Release 15.2]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
After performing a copy/paste of activities in P6 Pro Client from Project A to Project B, the codes and resources from Project A do NOT show up in Project B when only Project B is open.

EXPECTED BEHAVIOR
-----------------------
Activity codes and resource assignments will be displayed when only the target project is open.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Login P6
2. Open two projects A and B
3. Copy activity with activity code from project A to project B
4. Close all projects, then open the target project B
5. The activity code is missing in the target project B
6. The activity code is shown correctly if open both A and B


Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms