"Calculate Costs From Units" Box Is Unchecked For Project Imported From Microsoft Project (Doc ID 2097300.1)

Last updated on JANUARY 20, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 8.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 8.2.4.0 and later
Information in this document applies to any platform.

Symptoms

"Calculate costs from units" is not checked by default when importing a project from Microsoft Project. This causes the Cost to not recalculate when the resource rate is changed.

Cause