My Oracle Support Banner

How to Make Projects Ignore Other Project's Activities While Scheduling a Single Project (With External Relationships) When Linked Projects Are Closed? (Doc ID 2106103.1)

Last updated on SEPTEMBER 30, 2019

Applies to:

Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 15.1.0.0 and later
Primavera P6 Professional Project Management - Version 15.1.0.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 15.1.0.0 and later
Information in this document applies to any platform.

Goal

A project with external relationships was scheduled together with the related projects and the dates changed to reflect this.
But when the related projects were closed and the single project was scheduled, the dates didn't change back.
What setting controls the ability to remove ties to external activities during scheduling?
 

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.