Dates Are Partially Hidden By Bars In Gantt Chart And Not Clearly Visible (Doc ID 2108427.1)

Last updated on JUNE 27, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 8.0 and later
Primavera P6 Professional Project Management - Version 8.1.0.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 8.2.4.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
 
In the Activities window, dates are partially hidden by bars in Gantt chart and not clearly visible.

EXPECTED BEHAVIOR
-----------------------
Dates to be visible in Gantt chart

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Log into P6 client
2. Open a Project
3. Navigate to the Activities tab
4. Enable the Gantt Chart


 

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms