Why are Costs Rounding Up and Not Displaying the Currency Symbol?
(Doc ID 2112475.1)
Last updated on DECEMBER 23, 2021
Applies to:
Primavera P6 Professional Project Management - Version 7.0 and laterPrimavera P6 Enterprise Project Portfolio Management - Version 7.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 8.2.4.0 and later
Information in this document applies to any platform.
Symptoms
For Example: enter 45.73 for budgeted costs to an a resources that is assigned to an activity. After refreshing the project the budgeted costs reverts to 46/per hour.
Cause