Budget Remains In SUBMITTED STATUS. Unable to Base line Budget

(Doc ID 2115105.1)

Last updated on NOVEMBER 03, 2017

Applies to:

Oracle Fusion Project Control Cloud Service - Version 11.1.10.0.0 to 11.1.11.0.0 [Release 1.0]
Information in this document applies to any platform.

Symptoms



When attempting to Approve Budget,
the following error occurs.

ERROR
-----------------------

"Integrate Project Budget with Oracle Fusion Budgetary Control" Process goes into error


STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Manage Budgets and Create a new Budget Version
2. Submit for Approval
3. Approve the Budget



Cause