The Total For Budgeted Labor Units Does Not Correlate To The Amount When Manually Summarized. (Doc ID 2121356.1)

Last updated on APRIL 18, 2016

Applies to:

Primavera P6 Professional Project Management - Version 15.2.0.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 15.2.0.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 15.2.0.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
The total of the Resources are shown as more than the amount it is supposed to be. For instance, the total for Budged Labor Units shows 10,000 when it should be be 8,000 (counted manually).

EXPECTED BEHAVIOR
-----------------------
The summaries (roll-up) should depict the correct number.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Open P6 and go to Activities View.
2. Add Budgeted Labor Units to the columns.
3. Notice that the total is out of sync with the actual total for Budgeted Labor Units.

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot effectively notate the total of Budgeted Labor Units when in the Activity view.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms