Able To Submit Budget With Exceptions For Baseline (Doc ID 2123768.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Fusion Project Control Cloud Service - Version 11.1.10.0.0 and later
Information in this document applies to any platform.

Symptoms

On : 11.1.10.0.0 version, Other Issues

ACTUAL BEHAVIOR
---------------
 When a budget version with exceptions is created user is able to  Submit (Create baseline) for approval 
EXPECTED BEHAVIOR
-----------------------
The budget with exceptions should not be allowed to be submitted for baseline.

Cause

Sign In with your My Oracle Support account