Cost Displayed on Data Date Instead of Actual Date For Closed Activity (Doc ID 2125686.1)

Last updated on APRIL 18, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 8.1.0.0 and later
Primavera P6 Professional Project Management - Version 8.1.0.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 8.4.9.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
Actual Non Labor Cost is displayed on the Data Date instead of Actual date for closed activity.

Expected Result:
Activities That have Actual Start = Actual Finish dates in the past should place the Actual Nonlabor Cost in those dates, not in the Data Date.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Log into P6 client
2. Open a specific project
3. Notice the cost for certain activities are no longer on the actual date but on the Data Date

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms