Data Date Line in HTML 5 View Does Not Match the Data Date After Scheduling (Doc ID 2128540.1)

Last updated on MARCH 09, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 16.1.0.0 to 16.1.1.0 [Release 16.1]
Primavera P6 Enterprise Project Portfolio Management - Version 16.1.0.0 to 16.1.1.0 [Release 16.1]
Information in this document applies to any platform.

Symptoms

On : P6 Web Application

ACTUAL BEHAVIOR
---------------
When viewing Activities View in HTML 5, end user moves the Data Date (DD) out and schedule Projects. However, the DD line in the Gantt Chart does not move.

EXPECTED BEHAVIOR
-----------------------
DD line to match the DD when scheduling Project.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Log into P6 Web, open Project and go to the Activities View.
2. View Activities in HTML 5 mode.
3. Schedule Project and move DD out.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms