Numeric Activity ID's Imported From P3 Shift to the Left When Edited

(Doc ID 2130952.1)

Last updated on MAY 02, 2016

Applies to:

Primavera P6 Professional Project Management - Version 8.1.1.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 8.1.1.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 8.2.4.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
Activity ID imported into P6 does not consist with the source activity id in P3

EXPECTED BEHAVIOR
-----------------------
Activity ID should be same as original activity id in P6

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Login P6 Client
2. Import P3 Project into P6
3. Found Activity ID are not same as original Activity ID in P3

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot have same Activity ID after import

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms