My Oracle Support Banner

23083452 Any Change Of Resource Causes Change Back To Allocation% As 100% Therefore Duration Changes (Doc ID 2131162.1)

Last updated on OCTOBER 17, 2019

Applies to:

Oracle Fusion Project Management Cloud Service - Version 11.1.10.0.0 and later
Information in this document applies to any platform.

Goal

Rel 10 In the Project Management plan where if duration and effort are different against a task then any change of resource in Project Plan User Interface (UI) causes change in Allocation% back to 100% which leads to change in duration resulting in change in the downstream dependent tasks.

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.