% Complete (Percent Complete) For A Phase Activity Shows 0 Although Some Child Activities Have Completed (Doc ID 2131325.1)

Last updated on APRIL 29, 2016

Applies to:

Instantis EnterpriseTrack Cloud Service - Version 8.7 and later
Instantis EnterpriseTrack - Version 8.7 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
Modify the status of an activity to complete, the phase % Complete (percent complete) still shows "%0".

EXPECTED BEHAVIOR
-----------------------
The % Complete value of phase should be more than %0.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Open a project.
2. Navigate to Roadmap.
3. Complete an activity.

Cause